Activity Hazard Analysis
1- Grading and levelling of the land
Hazards using of machines there should be one or two people to accompany each machine for safety and to lead each machine.
2- Excavation
Hazards- using of machines during excavation- there should be one or two people to accompany the machine for safety and to lead each machine.
3- Placing sub-base material and back filling
Hazards using of machines there should be one or two people to accompany each machine for safety and to lead each machine.
4- Electrical installations
Installation and connection of the generator, lighting systems,Hazard- Electrical safety precaution tools
5- Concrete floor, pouring concrete
Hazards Track mixers movement, concrete pumps movement and control
6- Construction of latrine building
Hazards using machines for clearing and grubbing, excavation, Falling objects, electrical precautions when installing electric equipment.
8- Sewer Manholes:
Warning signs and rigid barricades shall be promptly placed when covers of manholes, hand-holes, or vaults are removed.
When working on buried cable or on cable in manholes, metallic sheath continuity shall be maintained by bonding across the opening or by equivalent means.